HAYLO / TRACK RECORD

Power that keeps care moving.

Five projects across Ethiopia, Uganda, Syria, and Lebanon. Built for the wards, classrooms, and communities where dependable power changes what is possible.

05

sites in the archive

04

countries reached

4.3M+

people in hospital catchments

01

Live

2025

Mudula Primary Hospital

Tembaro Special Woreda, Ethiopia

SCOPE

Design / Planning / Monitoring

STAKEHOLDERS

Weema

THE PROBLEM

Mudula Primary Hospital serves over 600,000 people across the Tembaro Special Woreda. An unreliable grid and costly diesel backup left critical devices at risk, while unstable cooling spoiled medicines and power surges regularly burned equipment.

THE SOLUTION

We designed and installed a 73.80 kWp solar system with 104.66 kWh of battery storage across 351 m² of rooftop. The system covers just over half of annual demand, stabilizes voltage for sensitive equipment, and keeps medicine storage at consistent temperatures.

Catchment area: 600,000 • Patients per month: 21,350 • Beds: 45

SYSTEM SIZE

73.80 kWp

NET SAVINGS / 10 YEARS

€281,521

BATTERY SIZE

104.66 kWh

SOLAR SURFACE

351 m²

ANNUAL DEMAND

246.14 MWh

ANNUAL YIELD

131.82 MWh

SOLAR RATIO

51.16%

CO₂ SAVINGS / 10 YEARS

76.05 t

02

Live

2026

Karat Primary Hospital

Konzo region, Ethiopia

SCOPE

Design / Planning / Monitoring

STAKEHOLDERS

ForAfrika

THE PROBLEM

Karat Primary Hospital treats over 7,000 patients each month for a catchment of 700,000 people in southern Ethiopia. Grid outages left the hospital dependent on diesel backup, while unstable power damaged devices and spoiled vaccines.

THE SOLUTION

A 128.00 kWp solar system with 122.80 kWh of battery storage now covers more than half of annual electricity demand. Incubators, surgical equipment, and vaccine refrigeration run on stable power.

Catchment area: 700,000 • Patients per month: 7,004 • Beds: 110

SYSTEM SIZE

128.00 kWp

NET SAVINGS / 10 YEARS

€322,258

BATTERY SIZE

122.80 kWh

SOLAR SURFACE

575 m²

ANNUAL DEMAND

325.27 MWh

ANNUAL YIELD

219.06 MWh

SOLAR RATIO

55.59%

CO₂ SAVINGS / 10 YEARS

963.30 t

03

Live

2026

Idlib University Hospital

Idlib, Syria

SCOPE

Design / Planning / Monitoring

STAKEHOLDERS

SAMS

THE PROBLEM

Idlib University Hospital treats over 7,000 patients each month for a catchment of roughly 2.9 million people. Incubators, ventilators, and vaccine refrigeration relied on grid power and diesel backup, costing around €12,000 a month.

THE SOLUTION

We structured a blended grant and loan financing model and installed a 128.00 kWp solar system across 575 m² of rooftop, targeting the hospital’s most critical wards and generating net savings from day one.

Catchment area: ~2,900,000 • Patients per month: ~7,000 • Beds: 70

SYSTEM SIZE

128.00 kWp

NET SAVINGS / 10 YEARS

€281,521

BATTERY SIZE

SOLAR SURFACE

575 m²

ANNUAL DEMAND

863.93 MWh

ANNUAL YIELD

SOLAR RATIO

22.73%

CO₂ SAVINGS / 10 YEARS

76.05 t

04

In progress

2026

Anaka General Hospital

Nwoya, Uganda

SCOPE

Design / Planning / Monitoring

STAKEHOLDERS

Empowering Africa

THE PROBLEM

Anaka General Hospital is the main referral center for its region in northern Uganda, treating over 1,000 patients a day with a single ambulance covering the whole area. Grid outages and voltage spikes have burned specialist equipment and spoiled vaccines.

THE SOLUTION

We are installing a 64.80 kWp solar system with a 122.80 kWh battery across 288 m² of rooftop, covering roughly 71% of annual demand. Electric motorbikes for patient transport will cut operating costs further.

Catchment area: 108,032 • Patients per month: 1,055 • Beds: 163 • Annual diesel expenses: €13,800

SYSTEM SIZE

64.80 kWp

NET SAVINGS / 10 YEARS

€155,401

BATTERY SIZE

122.80 kWh

SOLAR SURFACE

288 m²

ANNUAL DEMAND

110.00 MWh

ANNUAL YIELD

115.63 MWh

SOLAR RATIO

70.94%

CO₂ SAVINGS / 10 YEARS

602.10 t

05

Live

2024

Al Manhaj Schools

Tripoli, Lebanon

SCOPE

Design / Planning / Monitoring

STAKEHOLDERS

Al Manhaj, BILD hilft e.V. „Ein Herz für Kinder“

THE PROBLEM

Al Manhaj runs four schools and a disability center in Tripoli, serving children who are mostly Syrian refugees or from low-income Lebanese and Palestinian families. Lebanon’s grid delivers only a few hours of power a day, pushing schools onto expensive diesel and forcing cancelled classes.

THE SOLUTION

We designed, financed, and installed four off-grid solar systems with battery backup, sized to each rooftop and load profile. Removing diesel dependency freed close to $26,400 per school each year for tuition support and higher enrolment.

Ability Center • Dar International School • Darb Al Tabbaneh School • Lycée Modern

SYSTEM SIZE

75 kWp combined

NET SAVINGS / 10 YEARS

€233,900

BATTERY SIZE

91.3 kWh combined

SOLAR SURFACE

ANNUAL DEMAND

ANNUAL YIELD

SOLAR RATIO

CO₂ SAVINGS / 10 YEARS

1,300 t

Reliable power is public infrastructure.

Back to Haylo